Mudon construction site
Industry / Application | Construction |
Plant type | Solar-diesel hybrid |
Total capacity | 500 kVA |
Location | Mudon, Dubai, United Arab Emirates |
Contracted | February 2016 |
Deployed | March 2016 |
For a contractor currently working on a major residential project in Dubai, Enerwhere provided a full solar generator rental package for the site office on the basis of a power purchase agreement (PPA).
The system uses Enerwhere’s solar generator system synchronized to diesel generators to provide a cost-effective, reliable power supply 24/7. The power demand of the site office is largely driven by air-conditioners and peaks in the early afternoon. For this reason, Enerwhere set up the solar system with a slight tilt towards south-west, providing a near perfect match between solar power generation and the facility’s demand.